More work on updating project tasks.
Diffstat (limited to 'doc')
-rw-r--r--doc/internal_docs/project_schedule/dec12-jan8.tji5
-rw-r--r--doc/internal_docs/project_schedule/jan16-jan22.tji1
-rw-r--r--doc/internal_docs/project_schedule/jan9-jan15.tji7
-rw-r--r--doc/internal_docs/project_schedule/project_tasks.tjp17
4 files changed, 22 insertions, 8 deletions
diff --git a/doc/internal_docs/project_schedule/dec12-jan8.tji b/doc/internal_docs/project_schedule/dec12-jan8.tji
index c0d8909..a5bfaad 100644
--- a/doc/internal_docs/project_schedule/dec12-jan8.tji
+++ b/doc/internal_docs/project_schedule/dec12-jan8.tji
@@ -101,6 +101,11 @@ supplement task research.osx_research.osx_learn {
supplement task research.osx_research.xcode {
}
supplement task research.osx_research.obj_c {
+ booking bhuddle_r 2011-12-16 +2h {sloppy 2}
+ booking jvanderw_r 2011-12-16 +4h {sloppy 2}
+ booking askomra_r 2011-12-29 +4h {sloppy 2}
+ booking dsnyder_r 2011-12-28 +4h {sloppy 2}
+ booking bwooley_r 2011-12-15 +4h {sloppy 2}
}
supplement task research.osx_research.learn_apple_api {
}
diff --git a/doc/internal_docs/project_schedule/jan16-jan22.tji b/doc/internal_docs/project_schedule/jan16-jan22.tji
index 2692d40..35cb0c0 100644
--- a/doc/internal_docs/project_schedule/jan16-jan22.tji
+++ b/doc/internal_docs/project_schedule/jan16-jan22.tji
@@ -294,6 +294,7 @@ supplement task management.weekly_status_updates {
booking jvanderw_r 2012-01-20-13:00--0800 + 1.0h { overtime 2 }
}
supplement task management.weekly_wbs_update {
+ booking jvanderw_r 2012-01-19 +2h {sloppy 2}
}
supplement task management.weekly_schedule_update {
booking jvanderw_r 2012-01-19-13:00--0800 + 1.0h { overtime 2 }
diff --git a/doc/internal_docs/project_schedule/jan9-jan15.tji b/doc/internal_docs/project_schedule/jan9-jan15.tji
index ab420c6..019812d 100644
--- a/doc/internal_docs/project_schedule/jan9-jan15.tji
+++ b/doc/internal_docs/project_schedule/jan9-jan15.tji
@@ -98,10 +98,16 @@ supplement task research.code_bases.lightpipe {
supplement task research.osx_research {
}
supplement task research.osx_research.osx_learn {
+ booking jvanderw_r 2012-01-12 +2h {sloppy 2}
+ booking carrbs_r 2012-01-12 +0.5h {sloppy 2}
+ complete 100
}
supplement task research.osx_research.xcode {
}
supplement task research.osx_research.obj_c {
+ booking carrbs_r 2012-01-13 +4h {sloppy 2}
+ booking bhuddle_r 2012-01-15 +2h {sloppy 2}
+ complete 100
}
supplement task research.osx_research.learn_apple_api {
}
@@ -278,6 +284,7 @@ supplement task sys_admin.repo_mangement.repo_maint {
supplement task management {
}
supplement task management.weekly_status_updates {
+ booking jvanderw_r 2012-01-13 +2h {sloppy 2}
}
supplement task management.weekly_wbs_update {
}
diff --git a/doc/internal_docs/project_schedule/project_tasks.tjp b/doc/internal_docs/project_schedule/project_tasks.tjp
index a7b47bc..cf3bff4 100644
--- a/doc/internal_docs/project_schedule/project_tasks.tjp
+++ b/doc/internal_docs/project_schedule/project_tasks.tjp
@@ -127,7 +127,7 @@ shift two_hr_weekly "Two hours per week" {
# Project Documentation tasks
task documentation "Documentation" {
-
+ scheduling asap
task project_docs "Project" {
note "Documents generated for the use of the team in development."
@@ -375,6 +375,7 @@ task documentation "Documentation" {
} # end documentation
task research "Research" {
+ scheduling asap
note "Team wide research tasks."
# Depends on completing the project plan
depends !documentation.project_docs.proj_plan
@@ -404,7 +405,6 @@ task research "Research" {
${allocate_team}
}
task obj_c "Basic Objective-C familiarity" {
- depends !xcode
effort 24h
${allocate_team}
}
@@ -421,6 +421,7 @@ task research "Research" {
task a_and_d "Architecture and Design" {
depends !documentation.project_docs.proj_plan
${allocate_a_and_d}
+ scheduling asap
# Research task associated with Architecture and Design
task a_and_d_research "Research" {
@@ -587,7 +588,7 @@ task a_and_d "Architecture and Design" {
# Development task - specifically these are implementation tasks
task dev "Development" {
-
+ scheduling asap
task dev_mile0 "Milestone 0 development" {
task env_setup "Setup Environment Development" {
@@ -702,7 +703,7 @@ task dev "Development" {
} # end dev
task v_and_v "Validation and Verification" {
-
+ scheduling asap
task v_and_v_mile0 "Milestone 0" {
note "Validate the verify the first Milestone"
depends !!dev.dev_mile0
@@ -771,7 +772,7 @@ task v_and_v "Validation and Verification" {
# System Administration tasks
task sys_admin "System Administration" {
-
+ scheduling asap
task back_ups "Backup and recovery system" {
task back_up_plan "Identify back-up plan" {
note "Identify what it is that we are going to do for a back-up plan"
@@ -819,7 +820,7 @@ task sys_admin "System Administration" {
# Management tasks and meetings
task management "Management" {
# All of these tasks are currently weekly repeating
-
+ scheduling asap
task weekly_status_updates "Status and performance update" {
note "Weekly status and performance updates to be emailed to Bart"
start 2011-11-14
@@ -858,7 +859,7 @@ task management "Management" {
#Deployment and presentations
task deployment "Deployment and presentations" {
-
+ scheduling asap
task hand_off "Hand off to sponsors" {
note "Hand off the project to the sponsors. Since this is an open source project, the documentation and public git repository should be enough."
depends !!v_and_v.v_and_v_mile4
@@ -886,7 +887,7 @@ task deployment "Deployment and presentations" {
# Project Milestones
task project_milestones "Milestones" {
-
+ scheduling asap
task init_project_plan "Initial Project Plan Complete" {
milestone
depends documentation.project_docs.proj_plan